Permitting Support
Your solar interconnection application in Kentucky passes through several hands before the meter changes. We organize the paperwork, coordinate the handoffs and track every step until the utility says the system may run.
Interconnection is a switching yard. One misrouted form can idle the whole train for weeks.
A solar interconnection application in Kentucky isn’t one form. It’s a sequence, and each step waits on the one before it. Details differ by utility, but the general path looks like this:
Picture a rail switching yard. Your installer’s drawings, your account details and the local inspection travel on separate tracks, and all three have to reach the meter together. A single form sent down the wrong track can leave the whole project waiting on a siding. Our job is to throw the switches in the right order.
We don’t publish fees or day counts for specific utilities, because they change. We confirm current forms, fees and contacts for your utility when we start.
Kentucky’s interconnection and net metering guidelines date from 2009. The Public Service Commission is reviewing them in Case No. 2020-00302, and in 2026 it clarified that the review covers all behind-the-meter customers, including qualifying facilities that don’t use net metering. If your project is near or above 45 kilowatts, ask early which process applies. Our Kentucky net metering explainer covers how the credits work.
We collect your account information, confirm form versions, assemble the packet, flag signatures, track every step, follow up with the utility and local office, and keep the record. Your installer or a licensed professional prepares the technical drawings and does the electrical work. The local authority inspects. The utility decides. Calvin Rudd coordinates, and you hear from us at every change.
One habit worth copying: keep the date your net metering service began with your permanent records. Your credit terms can depend on it, and the paperwork that proves it is easy to lose.
If your installer closed before permission to operate, we can pick up the paperwork, and a System Health Check can show how the system itself is doing. HOA and local permit packets are covered in Approval & Incentive Packets, part of our broader permitting administrative support.
What you walk away with
Complete packets with the current form version, matching account details and every required attachment.
A tracker shows where the application sits, who has the next move and when we follow up.
Your installer, the local inspection office and the utility each get what they need from the others, on time.
Approval letters, the signed agreement and permission to operate, filed together for sale, refinance or warranty claims.
How it works
From the first form to permission to operate. We track the whole way and send a status update at every change.. You'll know the scope and the fee before any work begins.
A free 20-minute call to identify your utility and project size, and to see where things stand.
A written scope, deliverables, timeline and fixed fee before any work starts.
We collect account details, confirm the current forms and gather technical attachments from the licensed parties who prepare them.
With your authorization, the application is filed. We track review, agreement and conditions, and follow up on schedule.
We coordinate the completion notice, inspection record and meter change, then close the file when the utility grants permission to operate.
Deliverables
Where our work stops
Part of our Permitting Administrative Support practice. Also in this practice: Approval & Incentive Packets.
FAQ
Not until the utility says so. Kentucky utilities generally require an approved application, completed conditions and, for net metering, a meter change first. LG&E and KU, for example, grant permission to operate after installing the net meter. Running the system early can put you out of step with your utility's tariff.
Kentucky net metering covers eligible systems up to 45 kilowatts. Larger systems follow a different interconnection and compensation path, so check your utility's current tariff and process before the system is sized.
The general steps are similar, but each cooperative has its own tariff, forms and contacts. TVA-served co-ops and municipal utilities work through TVA's programs, which can look quite different from net metering. We confirm the current process for your utility before anything is filed.
Usually the utility account holder, sometimes together with the installer. Technical sections are completed by the installer or a licensed professional. We prepare the packet, flag every signature and check that names match the account exactly.
Not necessarily. Credit terms depend on your utility and on when your net metering service began, because new customers moved to different terms after recent PSC decisions. A neighbor's older system may still be on legacy terms.
Related
Policy & Incentives
How Kentucky net metering works after SB 100: legacy 1:1 credits, LG&E and KU's NMS-2 export credit, Kentucky Power, Duke, co-ops and the 45 kW limit.
Read more
Service
Assembly of HOA architectural review packets, local permit application packets and utility program, grant or loan paperwork, with a document log and a deadline calendar.
Read more
Service
A remote, data-driven check of one solar system, orphaned systems included: monitoring recovery, an expected-production baseline, a proposal comparison and a technician question list.
Read more
Who we serve
Independent help for Kentucky farm families weighing on-farm solar, comparing land lease offers, and sorting out co-op rules and 2026 program changes.
Read moreNext step
Tell us what you are weighing. A free 20-minute fit call is enough to know whether we can help and what it would take.