Sample reports: what you'll actually receive

Every solar feasibility report example below is illustrative, with hypothetical numbers, but the structure is exactly what our clients get: assumptions first, the answer in plain English, and the questions to take to your licensed professionals.

An open report with a pop-up paper landscape rising from its pages
The idea

A good report doesn't just give you an answer. It lets you see the landscape the answer came from.

What a solar feasibility report example should show you

Most people have never seen an independent solar report before they buy one, so here are six. Each sample below is a solar feasibility report example or a related deliverable, built on a hypothetical client with hypothetical numbers. The format, the order of sections, and the kind of tables are the same ones we deliver.

Every sample includes a report cover, its table of contents, and one excerpt table. The excerpts were chosen because each one turns up something a sales document wouldn’t: a financed price that runs above the cash price, a deadline that adds five years to payback, a low bid that leaves out required work, or a lease with lower starting rent that pays more over the full term.

Why the assumptions page comes first

A report’s conclusion is only as good as its inputs. So before any result, you see the utility rate path we assumed, the production model, degradation, discount rate, financing terms, and every other input that moves the answer, each with its source. If you disagree with one, you can tell us, and we’ll rerun the analysis during the follow-up round.

How to read the samples

  • Plain English first. The first page answers the question you asked, in a few sentences, before any table.
  • Tables you can check. Numbers are shown in a form you can recalculate. Nothing hides inside a black box.
  • Sensitivity, not false precision. We show how the answer changes when rates, production, or timelines change, because those are the inputs nobody knows for sure.
  • Clear limits. Where a decision needs a licensed engineer, electrician, attorney, or CPA, the report ends with a list of questions for them. We organize; they determine.

What the samples are not

They aren’t client work, and no figure in them describes a real person, business, or farm. They aren’t a forecast for your home or project, either. Your numbers depend on your utility, your tariff, your site, and your contract. For narrative versions of similar decisions, see our illustrative scenarios. To understand the timeline from documents to delivered report, read how it works, and for how pricing is set, see how our fees work.

Inside the binder

Six sample deliverables

Every figure below is hypothetical. The structure is exactly what you would receive.

14 pages · Proposal Second Opinion

Proposal Second Opinion

Illustrative: Fayette County homeowner, KU territory

An independent review of one 8.4 kWdc rooftop proposal offered four ways: cash, loan, lease, and PPA. The financed price runs $3,720 above the cash price, and the lease escalator outpaces the utility rate path we assumed, so only the cash option comes out clearly ahead over 25 years.

Ownership comparison, 25 years (nominal dollars)
OptionPaid up frontTotal paid, 25 yearsEst. bill savings, 25 yearsNet, 25 years
Cash purchase$24,780$27,380$37,740+$10,360
15-year loan, 6.49% APR$0$47,260$37,740−$9,520
25-year lease, $85/month, 2.9% escalator$0$36,700$37,740+$1,040
25-year PPA, 10.5¢/kWh, 2.9% escalator$0$35,620$37,740+$2,120

Ownership comparison, 25 years (nominal dollars)

Contents

  1. Summary: the answer on one page
  2. Assumptions page
  3. Price per watt and the cash-versus-financed gap
  4. Production estimate checked against an independent model
  5. Ownership comparison, 25 years
  6. Sensitivity: utility rates, production, and escalators
  7. Contract terms to raise with your attorney
  8. Questions for your installer and licensed professionals

Illustrative sample. Figures are hypothetical. About this service

Sample
36 pages · Commercial Feasibility Study

Commercial Feasibility Study

Illustrative: Central Kentucky manufacturer, one shift, KU commercial demand rate

A preliminary study of a 400 kWdc rooftop array, modeled against the federal credit deadlines that apply to solar projects starting construction in late 2026. Slipping past the December 31, 2027 placed-in-service date would add about five years to simple payback, which makes schedule risk the biggest variable in the decision.

Deadline scenarios, year-one view (tax items for your CPA to confirm)
ScenarioSystemFederal credit assumedNet cost after tax itemsYear-1 savingsSimple payback
A. In service by September 2027400 kWdc30% ($222,000)$385,910$38,00010.2 years
B. Slips to February 2028, credit lost400 kWdcNone$584,600$38,00015.4 years
C. Smaller array, in service June 2027250 kWdc30% ($146,250)$254,230$25,40010.0 years
D. Scenario A with utility rates 20% higher400 kWdc30% ($222,000)$385,910$45,6008.5 years

Deadline scenarios, year-one view (tax items for your CPA to confirm)

Contents

  1. Executive summary
  2. Assumptions page
  3. Load and interval data analysis
  4. Rate and demand charge review
  5. System size options matched to on-site use
  6. Deadline scenarios and schedule risk
  7. Cash flow, NPV, IRR, and payback
  8. Questions for your CPA, engineer, and attorney

Illustrative sample. Figures are hypothetical. About this service

Sample
12 pages · System Health Check

System Health Check

Illustrative: Jessamine County homeowner, installer out of business

Once monitoring access was recovered, this 7.2 kWdc system showed about half its weather-adjusted expected output from July through September 2026. The pattern is consistent with one of its two strings going offline in mid-June, and the report lists what to ask a qualified electrician to check and which manufacturer warranties may still apply.

Expected vs. measured production, April–September 2026
MonthExpected kWh (weather-adjusted)Measured kWhMeasured ÷ expected
April86081294%
May98092194%
June1,01070270%
July1,03052151%
August96048851%
September82041350%

Expected vs. measured production, April–September 2026

Contents

  1. Summary and next steps
  2. Assumptions page
  3. Monitoring access recovery log
  4. Expected vs. measured production, month by month
  5. Inverter and string data review
  6. Warranty documents located and their terms
  7. Questions for a qualified technician or electrician

Illustrative sample. Figures are hypothetical. About this service

Sample
18 pages · Installer RFP & Bid Leveling

Installer Bid Leveling

Illustrative: Louisville-area distribution warehouse, three rooftop bids

Three bids for a warehouse rooftop array of about 150 kWdc, rebuilt on the same scope so they compare line by line. The lowest total quote covers the smallest array and leaves out $14,200 of required work, so it lands in the middle on leveled price per watt.

Leveled bid comparison
Line itemBidder ABidder BBidder C
Quoted price$289,500$262,350$251,600
System size150.0 kWdc147.6 kWdc140.4 kWdc
Quoted price per watt$1.93$1.78$1.79
Excluded items, priced in$0$9,800$14,200
Leveled price per watt$1.93$1.84$1.89
Workmanship warranty10 years5 years2 years

Leveled bid comparison

Contents

  1. Summary and ranking
  2. Assumptions page
  3. Scope matrix: what each bid includes and excludes
  4. Equipment and warranty comparison
  5. Leveled price per watt
  6. Production estimates compared
  7. Clarification questions for each bidder
  8. Questions for your attorney and licensed professionals

Illustrative sample. Figures are hypothetical. About this service

Sample
10 pages · Carbon & Scope 2 Reporting

Scope 2 Inventory Memo

Illustrative: Bluegrass-region parts manufacturer, three sites

A first-year, non-certified Scope 2 estimate for 2025 electricity use at three sites, reported both location-based and market-based. Because the main plant's utility has a higher emission rate than the regional grid average, the market-based total comes out higher than the location-based one, even after the warehouse's RECs.

Scope 2 summary, calendar year 2025 (metric tons CO2e)
SiteElectricity (MWh)Location-basedMarket-basedMarket-based basis
Main plant4,8202,024.42,410.0Utility-specific rate
Warehouse610256.20.0RECs retired, 610 MWh
Office10042.050.0Utility-specific rate
Total5,5302,322.62,460.0Both methods reported

Scope 2 summary, calendar year 2025 (metric tons CO2e)

Contents

  1. Summary for your customer questionnaire
  2. Assumptions page and emission factor sources
  3. Electricity data by site and month
  4. Location-based results
  5. Market-based results and instruments held
  6. Data gaps and how we handled them
  7. What would change next year's number
  8. Limitations of a non-certified estimate

Illustrative sample. Figures are hypothetical. About this service

Sample
16 pages · Land Lease Offer Review

Land Lease Offer Comparison

Illustrative: Western Kentucky grain farm family, 180 acres under offer

Two utility-scale solar lease offers for the same 180 acres, compared on commercial and financial terms only. Offer B starts $100 an acre higher, but Offer A's 2% escalator passes it in year 7 and pays about $1.66 million more if every extension is exercised.

Two offers, full-term view (nominal dollars)
TermOffer AOffer B
Option period3 years at $40/acre5 years at $25/acre
Starting rent$850/acre/year$950/acre/year
Annual escalator2.0%None
Operating term25 years + two 5-year extensions20 years + three 5-year extensions
Total payments, 180 acres, full term$7.67 million$6.01 million
Decommissioning securityBond posted before constructionNot addressed in offer

Two offers, full-term view (nominal dollars)

Contents

  1. Summary of financial differences
  2. Assumptions page
  3. Payment schedules, year by year
  4. Option period and extension terms compared
  5. Present value of each offer at three discount rates
  6. Acreage, access, and crop-loss terms compared
  7. Decommissioning and security terms as written
  8. Questions for your attorney and accountant

Illustrative sample. Figures are hypothetical. About this service

Sample

What every report includes

  • An assumptions page up front, listing every input that moves the result and where it came from.
  • A one-page summary in plain English that answers the question you asked.
  • Tables you can check line by line, with sources for tariffs, weather data, and emission factors.
  • A sensitivity section showing which assumptions change the answer and by how much.
  • A list of questions for your licensed engineer, electrician, attorney, or CPA, when your decision needs one.
  • A recorded walkthrough call and one round of follow-up questions.